Thursday, March 05, 2009

We've been busy

Our Grand Opening has been set for Tuesday, April 14th at 10:00 a.m. - during National Library Week.

Staff is busy working inside - loading the shelves with books, DVDs, CDs and installing computers. Landscaping is in progress on the grounds.



Please enjoy this slideshow preview.


Thursday, November 13, 2008

What's going on and when will we open?

Our building is nearing completion. Construction should wrap up before Thanksgiving. Our furniture begins to arrive in December and installation happens in January. We will also begin moving in books, AV materials, and computers in January. We hope to open in February, so check this site in a few weeks for more information. Meanwhile, here are a few pictures from this week.







Saturday, September 20, 2008

September 2008

The month started with Gustav and continued with Ike. I'm happy to report that the facility withstood the winds and the rains. The rain that followed slowed down outside progress a bit, but much progress has been since August.

So when will we open? That seems to be the question everyone is asking. We anticipate the construction to be complete sometime in October and hope to accept the building in November. We will then spend time moving in furniture, computers, book collection and staff and hope to open early in 2009. The landscaping bids open this Tuesday (September 23rd).

The traffic signal at Johnston/Duhon (the library's intersection) is now operational and the road will be open by the time the library opens. (Currently you can access Duhon Road only to get to Giles Nissan/Volvo.)

Mike - the auditorium chairs were being installed on Friday. I hope you enjoy viewing those photos.

This photo show includes pictures from the monthly site meeting on September 9th and from a site visit on September 19th.


If the slideshow doesn't work on your browser, you can view the individual photos at
the Picasa Web site